After the stone work was completed, our project went a bit off track. A piece of the existing house was being replaced to accommodate a new porch light when some rotten wood was discovered. Removing that wood led to finding more rotten wood in the wall under Clara's window. And then investigating that led to finding rotten trim around Clara's window. So, we ended up replacing the window trim pieces and the wood inside the wall under her window. Since plywood wasn't around in 1938 when the house was built, the exterior walls were built with 2x6s, so some of those got replaced. The fixed area needs to be painted next, and then it is good as new.
Thursday, December 31, 2020
2020's Parting Gift
Tuesday, December 8, 2020
Masonry work
The last two weeks have been spent on the shiplap ceiling and the masonry work for the wall near the stairs and the fireplace.
The stone had to be moved under the roof with makeshift plastic walls around the porch and heaters to thaw the frozen stone. We lost several days of progress thanks to this step.
Tuesday, November 24, 2020
Progress is messy
Last week and into the weekend, the project went through a messy phase with spray foam insulation installation and the roof being completed.
Sunday, November 15, 2020
Siding, Electrical, and Fire!
Lots of progress here the past couple of weeks!
Cedar siding went on, the electrical and gas work are done, and we have a working fireplace!
Tuesday, November 3, 2020
It's a structure!
Lots of progress here the past couple of weeks. Headers and fireplace framing went in a week and a half ago, and then trusses arrived last Thursday. This week, the trusses were installed and the plywood layer of the roof was installed. It is really looking more like a structure now.
Tuesday, October 20, 2020
We've gone vertical!
In the past few weeks, the foundation was poured and the walk-out stairs were completed. We're back to a concrete slab now, but there's lots of infrastructure below that slab that wasn't there before for drainage and gas lines.
Friday, October 2, 2020
Porch - two weeks in
It's hard to believe we've been at this project for two weeks already. There was a slight delay this week with some rain, but other than that, things are moving along, though it doesn't look like much yet.
In the past week, a lot of dirt was removed so that the foundation walls and new drainage could be installed. Some additional drainage work also had to be done to keep water from running towards the kitchen door, so that work got more of the old patio involved than originally planned.
Trenches were dug for the footing for the foundation wall to sit on.
These two pictures show most of the yard before the additional concrete was cut up for the additional drainage.Wednesday, September 23, 2020
Our Next Project!
With so much time at home and so many mosquitoes in our neighborhood (thanks trees!), we decided our family would really enjoy a screened-in porch. It has taken several months of planning but the project is finally underway.
Here are the architectural drawings showing where the porch will be, relative to the existing house. Our basement walk-out needs some structural work and a new roof over it, so those problems are being addressed with this project too.