Somehow time got away from us, and it's May!
After the masonry work, a lot of the trim work was done. We waited a few weeks for screens and a few more for gutters and then a few more for weather.
Somehow time got away from us, and it's May!
After the masonry work, a lot of the trim work was done. We waited a few weeks for screens and a few more for gutters and then a few more for weather.
After the stone work was completed, our project went a bit off track. A piece of the existing house was being replaced to accommodate a new porch light when some rotten wood was discovered. Removing that wood led to finding more rotten wood in the wall under Clara's window. And then investigating that led to finding rotten trim around Clara's window. So, we ended up replacing the window trim pieces and the wood inside the wall under her window. Since plywood wasn't around in 1938 when the house was built, the exterior walls were built with 2x6s, so some of those got replaced. The fixed area needs to be painted next, and then it is good as new.
The last two weeks have been spent on the shiplap ceiling and the masonry work for the wall near the stairs and the fireplace.
The stone had to be moved under the roof with makeshift plastic walls around the porch and heaters to thaw the frozen stone. We lost several days of progress thanks to this step.
Last week and into the weekend, the project went through a messy phase with spray foam insulation installation and the roof being completed.
Lots of progress here the past couple of weeks!
Cedar siding went on, the electrical and gas work are done, and we have a working fireplace!
Lots of progress here the past couple of weeks. Headers and fireplace framing went in a week and a half ago, and then trusses arrived last Thursday. This week, the trusses were installed and the plywood layer of the roof was installed. It is really looking more like a structure now.
In the past few weeks, the foundation was poured and the walk-out stairs were completed. We're back to a concrete slab now, but there's lots of infrastructure below that slab that wasn't there before for drainage and gas lines.